Jan 25, 2017

Sewer construction work is scheduled to take place through the night time hours at the intersection of Sooke and Metchosin Roads between February 6 and February 10, 2017. Completing this intensive phase of work between 7 pm and 7 am will reduce major traffic congestion at the intersection. 

C-1 Contracting Ltd. began work in December 2016 to expand sewer lines between Hatley Park Mall on Sooke Road, up Metchosin Road to Allandale Road. 

While the work is not expected to disrupt traffic continuously, there will be periods between now and June 2017 when roads will be affected. Although single lane traffic will be maintained at all times, with two lanes maintained in the peak direction during morning and evening commutes, sporadic delays should be expected. 

Read more details about this project at Sewer expansion work to begin on Sooke & Metchosin Roads.