May 2, 2016

Where:        Metchosin Road at Painter Road

When:          May 2, 2016 for approximately three weeks

What:           Sanitary sewer service connection


Work on the sanitary sewer main to service the new development at  3319 Painter Road and 3320 Metchosin Road will begin on Monday, May 2, 2016.

Construction is expected to continue for approximately 3 weeks.

Work will begin on Metchosin Road between May 2 and May 4, with the remainder of the work taking place on Painter Road. 

Two lanes of uninterrupted traffic will be maintained during peak hours from 7am - 9am and 2:30pm - 4pm. Alternating traffic may be expected outside of those times. 

York Excavating is the contractor undertaking the work.